Multifamily Rehabilitation & Adaptive Reuse
505 Garden Street
Ivy Gardens
Little Falls, New York
- Location
- Little Falls, New York
- Category
- Multifamily Rehabilitation & Adaptive Reuse
- Current Status
- Completed
- Canalstone’s Role
- Founder-Led Experience
Project Overview
Overview
Ivy Gardens is the comprehensive redevelopment of a former residential building into a modern 21-unit apartment community in Little Falls, New York.
Originally constructed in 1950, the building underwent a substantial renovation that transformed aging residential spaces into contemporary apartments while modernizing essential building systems. The project included major electrical, plumbing, HVAC, fire-protection, and interior improvements, along with renovated common areas and upgraded building access systems.
The finished property offers a mix of studio, one-bedroom, and two-bedroom apartments designed for modern residential living.
Canalstone’s Involvement · Founder-Led Experience
Ivy Gardens was completed under the leadership of Canalstone’s founder before Canalstone Construction Group LLC was formed in November 2026. It is presented as the founder’s construction and redevelopment experience.
At a Glance
Project Details
- Construction Start
- November 2025
- Completion
- November 2026
- Duration
- 12 months
- Property Type
- Multifamily residential
- Size
- 21 apartments
- Originally Built
- 1950
The Work
Scope of Work
- Complete renovation of 21 residential apartments
- Interior demolition and reconfiguration
- Framing, drywall, painting, and finish carpentry
- New kitchens, cabinetry, countertops, and appliances
- Complete bathroom renovations and plumbing fixture upgrades
- New flooring, doors, trim, and interior finishes
- Electrical modernization, including an 800-amp three-phase service
- High-efficiency mini-split heating and cooling systems
- Plumbing infrastructure improvements
- Fire sprinkler and life-safety system improvements
- Insulation, window, and energy-efficiency upgrades
- Renovated hallways, entrances, and common areas
- Modern building access-control systems
- Coordination of inspections and construction closeout
Milestones
Construction Timeline
November 2025
Construction Begins (Complete)
Initial demolition, building evaluation, and construction preparation.
Winter–Spring 2026
Infrastructure Improvements (Complete)
Electrical, plumbing, HVAC planning, and building-system upgrades.
Spring–Summer 2026
Apartment Renovations (Complete)
Interior construction, kitchens, bathrooms, flooring, drywall, and finishes.
Summer–Fall 2026
Building Completion (Complete)
Mechanical installation, common-area improvements, inspections, and final construction work.
November 2026
Project Completed (Complete)
Completion of the 21-unit residential redevelopment.
Transformation
Before & After










Photography
Project Gallery
Related Projects
All Projects
Property Rehabilitation & Improvement
21194 State Route 22
Upstate New York

Commercial Redevelopment
1 West Main Street
Little Falls, New York

Historic Commercial Rehabilitation & Adaptive Reuse
2 West Main Street
Little Falls, New York

Commercial Adaptive Reuse & Property Repositioning
257 N. Main Street
Herkimer, New York